Concrete Pour
A working hour variance has been approved for a concrete pour on January 11 and 12. Working hours on these dates will be from 2:00 A.M. to 9:00 P.M.
Additional off-hours work activities will be limited in scope to pouring and finishing Tent Slabs in the pre-cast area, Lid Pour in SUT 1, and support activities associated with site winter weather preparation with a combined expected crew of less than 90. To minimize noise generation, offsite deliveries will be prohibited.