Concrete Pours

A concrete pour is scheduled for Jan. 3 from 2 a.m. to 9 p.m. Jan. 4 will be used as a contingency if the Jan. 3 date is pushed.

The concrete pour includes an expected crew of less than 30. To minimize noise generation, Bechtel will prohibit offsite deliveries.

Potential impacts to residents or business will be taken into consideration and monitored.