A work hour variance has been approved for:

•   Saturday, February 22 from 3:00 a.m. to 7:00 a.m.

•   Sunday, February 23 from 1:00 a.m. to Monday, February 24 at 5:00 a.m.

The additional weekend work hours allow for a mass concrete pour in the central area of the site with an estimated crew of less than 75. A work hour variance was also approved for work related to waterproofing, rebar and spread footing excavations, with workers entering through Gate 5.

To minimize noise generation, offsite deliveries will be prohibited (except emergency Batch Plant support functions) and backup alarms will be replaced with “shusher” style alarms. Light plants will be pointed downward to minimize disturbance. The majority of traffic through the gate will occur during normal working hours. After hours, gates furthest from existing properties will be utilized.

Other potential impacts to residents or business will be taken into consideration and monitored.